WEEKLY UPDATES:

Week of April 3, 2017

-  Traffic Signal Work to begin at Eaton Street and Erie Street – Traffic to be maintained –
    All work off the travel lanes

-   Asphalt Patching on Detour Routes and Repairs – Flag Control As Needed

 

Week of April 10, 2017

-  Temporary Signal at Eaton Street and Erie Street will be in Flash Mode

-  Traffic Control Devices will be delivered to project site and stage off the roadway.

Week of April 17, 2017

-          Place Signs, Sign Covers, Barricades and Detour Route and Close M-99 (Superior St) from
           Ash Street to Michigan Ave

-          Maintain Access to Business’ with Pedestrian Barricades

-          Saw cut Concrete Sidewalk and Begin Roadway Brick and Concrete Removals

-          Remove Trees

Week of April 24, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Maintain Access to Business’ with Pedestrian Barricades

-          Brick Road Removal

-          Concrete Curb and Gutter Removals

-          Concrete Sidewalk Removals

Week of May 1, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street and Erie Street to Remain Open

-          Maintain Access to Business’ with Pedestrian Barricades

-          Watermain Installation – Anticipated Service Shut Downs Identified Next Week

-          Storm Sewer Installation