Week of April 3, 2017

-  Traffic Signal Work to begin at Eaton Street and Erie Street – Traffic to be maintained –
    All work off the travel lanes

-   Asphalt Patching on Detour Routes and Repairs – Flag Control As Needed

 

Week of April 10, 2017

-  Temporary Signal at Eaton Street and Erie Street will be in Flash Mode

-  Traffic Control Devices will be delivered to project site and stage off the roadway.

Week of April 17, 2017

-          Place Signs, Sign Covers, Barricades and Detour Route and Close M-99 (Superior St) from
           Ash Street to Michigan Ave

-          Maintain Access to Business’ with Pedestrian Barricades

-          Saw cut Concrete Sidewalk and Begin Roadway Brick and Concrete Removals

-          Remove Trees

Week of April 24, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Maintain Access to Business’ with Pedestrian Barricades

-          Brick Road Removal

-          Concrete Curb and Gutter Removals

-          Concrete Sidewalk Removals

Week of May 1, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street and Erie Street to Remain Open

-          Maintain Access to Business’ with Pedestrian Barricades

-          Watermain Installation – Anticipated Service Shut Downs Identified Next Week

-          Storm Sewer Installation

Week of May 8, 2017

-         M-99 (Superior St) Closed from Ash Street to Michigan Ave

-         Cass Street to Close Mid-Week – for 2 – 3 Days

-         Erie Street to Remain Open

-         Maintain Access to Business’ with Pedestrian Barricades

-         Storm Sewer Installation

Week of May 15, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Close End of the Week – for 2 -3 Days

-          Erie Street to Remain Open

-          Pedestrians to Cross at Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Water main Installation – Erie St to Ash St – No Anticipated Service Shut Downs

-          Storm Sewer Installation to Begin End of Week

Week of May 22, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Remain Open

-          Erie Street to Remain Open

-          Pedestrians to Cross at Cass and Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Water main Pressure Testing

-          Water main Service Installation – Starting at Cass and Moving to South – Scheduled Service Shut Downs

-          Storm Sewer Installation – Starting at Cass and Moving to South

-          No Work During Memorial Day Weekend

Week of May 29, 2017 (No Work on Monday, May 29th)

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Remain Open

-          Erie Street to Close for Storm Sewer Crossing – for 2 -3 Days

-          Pedestrians to Cross at Cass and Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Water main Service Installation – Moving to the South – Scheduled Service Shut Downs

-          Storm Sewer Installation to Continue

Week of June 5, 2017 

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Remain Open

-          Erie Street to Remain Open

-          Pedestrians to Cross at Cass and Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Water main Service Lead Connections – Scheduled Service Shut Downs

-          Storm Sewer Installation to Continue

-          AT&T Installing New Ducts on West Side of S. Superior St

 

  Attached is the Progress Schedule for comparison.

-  The Water main original schedule controlling operation was to be completed on May 26th. This is not completed and is behind original schedule.

- Strom Sewer installation was scheduled as controlling operation starting on May 30th. This has already started and is ahead of schedule.

-  Brick Pavers are scheduled to begin on July 5th.

Week of June 12, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Remain Open

-          Erie Street to Remain Open

-          Pedestrians to Cross at Cass and Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Water main Service Installation – Scheduled Water Service Shut Downs for Building Cut Ins

-          Building Owners to be Notified by the City of Albion

-          Storm Sewer Installation at South End

-          AT&T Installing New Ducts on West Side of S. Superior St

 

Week of June 19, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Remain Open

-          Erie Street to Remain Open

-          Pedestrians to Cross at Cass and Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Water main Service Installation – Scheduled Water Service Shut Downs for Building Cut Ins

-          Building Owners to be Notified by the City of Albion

-          Abandon Existing Water main

-          AT&T Installing New Ducts on West Side of S. Superior St 

Week of June 26, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Remain Open

-          Erie Street to Remain Open

-          Pedestrians to Cross at Cass and Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Water main Service Installation – Scheduled Water Service Shut Downs for Building Cut Ins

-          Building Owners to be Notified by the City of Albion

-          Abandon Existing Water main

-          AT&T Installing New Ducts on West Side of S. Superior St

-          Earth Excavation and  Grading Subgrade

-          Underdrain Installation

 Week of July 2, 2017

-         NO WORK JULY 1st – JULY 4th

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Remain Open

-          Erie Street to Remain Open

-          Pedestrians to Cross at Cass and Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Earth Excavation and  Grading Subgrade

-          Underdrain Installation

-          Curb and Gutter Installation

The Cass Street and M-99 intersection is going to be closing to traffic on Wednesday, July 5th

Cass Street will be closed for approximately 2-3 weeks for water main connections, storm sewer installation,
earth excavation, sand and gravel base course and concrete base course. 

Erie Street will remain open during this time frame. 

The Closure of Cass Street has been delayed until Thursday, July 6th.

 

Week of July 17, 2017

-         M-99 (Superior St) Closed from Ash Street to Michigan Ave

-         Cass Street to Remain CLOSED

-         Erie Street to Remain Open

-         Pedestrians to Cross at Erie Street

-         Maintain Access to Business’ with Pedestrian Barricades

-         Complete Storm Sewer Cass Street to River

-         Grade and Install Curb and Gutter Ash Street to Erie Street

-         Install Concrete Valley Gutter and Bridge Deck Approach

-         Gravel Base Course Installation and Grading

-         Grade for Sidewalk

 

Week of July 24, 2017

-         M-99 (Superior St) Closed from Ash Street to Michigan Ave

-         Cass Street to Remain CLOSED

-         Erie Street to Remain Open

-         Pedestrians to Cross at Erie Street

-         Maintain Access to Business’ with Pedestrian Barricades

-         Gravel Base Course Installation

-         Grade for Sidewalk

-         Concrete Base Course Installation

               




 

 

 