 2018  WEEKLY UPDATES: 


    construction schedule june1website




mdot construction schedulewebsite

brick construction schedule
const schdule may 2018website
 

construction schedule junewebsite          


construction july website



construction schedule julywebsite









Week of May 7, 2018

  • MAY 7th      SET-UP DETOURS on M-99 and I-94BL (Michigan Ave)
  • M-99      (Superior St) Closed from Cass St to Mulberry St
  • Michigan      Ave Closed from Post Office to Ionia St
  • Cass      Street Open
  • Erie      Street Open
  • Pedestrians to Cross at Cass Street and Mulberry Street
  • Maintain Access to Business’ with Pedestrian Barricades
  • Asphalt Pavement Removal
  • Prep and Clean Concrete Base Course 

Week of May 14, 2018

  • M-99      (Superior St) Closed from Cass St to Mulberry St
  • Michigan      Ave Closed from Post Office to Ionia St
  • Cass      Street Open
  • Erie      Street Open
  • Pedestrians to Cross at      Cass Street and Mulberry Street
  • Maintain Access to
         Business’ with Pedestrian Barricades
  • Asphalt Paving –      Michigan Ave to Vine St

Week of May 21, 2018

    • M-99      (Superior St) Closed from Cass St to Mulberry St
    • Michigan      Ave Closed from Post Office to Ionia St
    • Cass      Street Open
    • Erie      Street Open
    • Pedestrians to Cross at      Cass Street and Mulberry Street
    • Maintain Access to      Business’ with Pedestrian Barricades
    • Install Bricks –      Michigan Ave to Vine St  

Week of May 28, 2018

  • NO WORK ON MONDAY – MEMORIAL DAY
  • M-99      (Superior St) Closed from Cass St to Mulberry St
  • Michigan      Ave Closed from Post Office to Ionia St
  • Cass      Street Open
  • Erie      Street Open
  • Pedestrians to Cross at      Cass Street and Mulberry Street
  • Maintain Access to Business’      with Pedestrian Barricades
  • Install Bricks –      Michigan Ave to Vine St

Week of June 4th, 2018

  • M-99      (Superior St) Open from Cass St to Mulberry St
  • Michigan      Ave Open from Post Office to Ionia St
  • M-99      (Superior St) Closed from Michigan Ave to Ash St
  • Cass      Street Closed
  • Erie      Street Open
  • Pedestrians to Cross at      Cass Street and Erie Street
  • Maintain Access to      Business’ with Pedestrian Barricades
  • Remove Brick Pavers
  • Prep and Clean Concrete      Base Course

Currently, one week behind on completion of Stage 3 (North Section).

 Stage 1 and 2 (South Section) is still anticipated to be completed the week of August 27th. The one week behind should be made up during the 10 weeks for brick installation, due to learning curve of new process and longer hours as needed.

Week of June 11th,  2018

  • M-99      (Superior St) Open from Cass St to Mulberry St
  • Michigan      Ave Open from Post Office to Ionia St
  • M-99      (Superior St) Closed from Michigan Ave to Ash St
  • Cass      Street Closed
  • Erie      Street Open
  • Pedestrians to Cross at Cass Street and Erie Street
  • Maintain Access to Business’ with Pedestrian Barricades
  • Remove Brick Pavers
  • Prep and Clean Concrete Base Course
  • Ultra Thin Asphalt Paving

 

Week of June 18th,  2018

  • M-99      (Superior St) Open from Cass St to Mulberry St
  • Michigan      Ave Open from Post Office to Ionia St
  • M-99      (Superior St) Closed from Michigan Ave to Ash St
  • Cass      Street Closed
  • Erie      Street CLOSED
  • Pedestrians to Cross at Cass Street and Erie Street
  • Maintain Access to Business’ with Pedestrian Barricades
  • Ultra Thin Asphalt Paving
  • Install Brick

    Brick available to residents have been stockpiled at Mulberry and Monroe Streets

     

    Construction Open House at the Ludington Center 9-10:00 am on Wednesday – June 27th

     

    Week of June 25th,  2018

    • M-99      (Superior St) Open from Cass St Michigan Ave to Mulberry St
    • Michigan      Ave Open from Post Office to Ionia St
    • M-99      (Superior St) Closed from Michigan Ave to Ash St
    • Cass      Street Closed
    • Erie      Street CLOSED – SUNDAY, MONDAY, TUESDAY and WEDNESDAY
    • Pedestrians to Cross at      Cass Street and Erie Street
    • Maintain Access to      Business’ with Pedestrian Barricades
    • Ultra Thin Asphalt      Paving
    • Install Brick

     

    Week of July 2nd,  2018

    • M-99      (Superior St) Open from Cass St to Mulberry St
    • Michigan      Ave Open from Post Office to Ionia St
    • M-99      (Superior St) Closed from Michigan Ave to Ash St
    • Cass      Street Closed
    • Erie      Street OPEN
    • Pedestrians to Cross at      Cass Street and Erie Street
    • Maintain Access to      Business’ with Pedestrian Barricades
    • Install Brick

Week of July 9th,  2018

  • M-99      (Superior St) Open from Michigan Ave to Mulberry St
  • Michigan      Ave Open from Post Office to Ionia St
  • M-99      (Superior St) Closed from Michigan Ave to Ash St
  • Cass      Street Closed
  • Erie      Street OPEN
  • Pedestrians to Cross at      Michigan Avenue, Erie Street and Ash Street
  • Maintain Access to      Business’ with Pedestrian Barricades
  • Install Brick

Week of July 16th,  2018

  • M-99      (Superior St) Open from Michigan Ave to Mulberry St
  • M-99      (Superior St) Closed from Michigan Ave to Ash St
  • Cass      Street Closed
  • Erie      Street OPEN
  • Pedestrians to Cross at      Michigan Avenue, Erie Street and Ash Street
  • Maintain Access to      Business’ with Pedestrian Barricades
  • Install Brick

 

A small stockpile of bricks are available at Mulberry and Monroe Streets for residents

 

Construction Open House at the Ludington Center 9-10:00 am on Wednesday – July 25th 

Week of July 23rd,  2018

  • M-99      (Superior St) Open from Michigan Ave (moving to Cass St during the week)      to Mulberry St
  • Michigan      Ave Open from Post Office to Ionia St
  • M-99      (Superior St) Closed from Michigan Ave to Ash St
  • Cass      Street Closed (moving to Open during the week)
  • Erie      Street OPEN
  • Pedestrians to Cross at      Michigan Avenue, Erie Street and Ash Street
  • Maintain Access to      Business’ with Pedestrian Barricades
  • Install Brick

A small stockpile of bricks are available at Mulberry and Monroe Streets for residents

 

Construction Open House at the Ludington Center 9-10:00 am on Wednesday – August 8th

 Week of July 23rd,  2018

  • Cass      Street Closed (moving to Open during the week)Saturday or Monday Cass St to Open  

Week of July 30th,  2018

  • M-99      (Superior St) Open from Michigan Ave to Cass St
  • Michigan      Ave Open from Post Office to Ionia St
  • M-99      (Superior St) Closed from Cass Ave to Ash St
  • Cass      Street OPEN
  • Erie      Street OPEN
  • Pedestrians to Cross at      Michigan Avenue, Cass St, Erie Street and Ash Street
  • Maintain Access to      Business’ with Pedestrian Barricades
  • Install Brick 

A small stockpile of bricks are available at Mulberry and Monroe Streets for residents 

Construction Open House at the Ludington Center 9-10:00 am on Wednesday – August 8th

 Week of August 6th,  2018

  • M-99      (Superior St) Open from Michigan Ave to Cass St
  • Michigan      Ave Open from Post Office to Ionia St
  • M-99      (Superior St) Closed from Cass Ave to Ash St
  • Cass      Street OPEN
  • Erie      Street (TO CLOSE)
  • Center Street to Open      End of Week
  • Pedestrians to Cross at      Michigan Avenue, Cass St,  and Ash Street
  • Maintain Access to      Business’ with Pedestrian Barricades
  • Install Brick 

Week of August 13th,  2018

  • M-99      (Superior St) Open from Michigan Ave to Center St
  • Michigan      Ave Open from Post Office to Ionia St
  • M-99      (Superior St) Closed from Center St to Ash St
  • Cass      Street OPEN
  • Erie      Street (CLOSED)
  • Center      Street OPEN
  • Pedestrians to Cross at      Michigan Avenue, Cass St, Center Street and Ash Street
  • Maintain Access to      Business’ with Pedestrian Barricades
  • Install Brick

 

Construction Open House at the Ludington Center 9-10:00 am on Wednesday – August 22nd

 

Center Street was not opened this week as the sealing of brick requires 2 days of dry weather. 

Week of August 20th,  2018

  • M-99      (Superior St) Open from Michigan Ave to Center St
  • Michigan      Ave Open from Post Office to Ionia St
  • M-99      (Superior St) Closed from Center St to Ash St
  • Cass      Street OPEN
  • Erie      Street (CLOSED)
  • Center      Street OPEN
  • Pedestrians to Cross at      Michigan Avenue, Cass St, Center Street and Ash Street
  • Maintain Access to      Business’ with Pedestrian Barricades
  • Install Brick

 

Week of August 27th,  2018 

  • M-99      (Superior St) Open from Michigan Ave to Center St
  • Michigan      Ave Open
  • M-99      (Superior St) Closed from Center St to Ash St
  • Cass      Street OPEN
  • Erie      Street (CLOSED)
  • Center      Street OPEN
  • Pedestrians to Cross at      Michigan Avenue, Cass St, Center Street and Ash Street
  • Maintain Access to      Business’ with Pedestrian Barricades
  • Install Brick
  • Pavement Markings
  • Open Road
  •  

2 days of wet weather this delayed the completion and opening of M-99

 

Week of September 3rd, 2018 

  • M-99      (Superior St) Open from Michigan Ave to Center St
  • Michigan      Ave Open
  • M-99      (Superior St) Closed from Center St to Ash St
  • Cass      Street OPEN
  • Erie      Street (CLOSED)
  • Center      Street OPEN
  • Pedestrians to Cross at      Michigan Avenue, Cass St, Center Street and Ash Street
  • Maintain Access to      Business’ with Pedestrian Barricades
  • Install Brick
  • Pavement Markings
  • OPEN      ROAD END OF THIS WEEK 

All the brick and joint sand is place.   

Wet weather this week has caused additional delays.  The joint sand needs to be dry in order for the joint sand stabilizer to soak in. 

Remaining work is joint sand stabilizer requiring 24 hours of dry weather. 

Week  of September 10, 2018

  • M-99      (Superior St) Open from Michigan Ave to Center St
  • Michigan      Ave Open
  • M-99      (Superior St) Closed from Center St to Ash St
  • Cass      Street OPEN
  • Erie      Street (CLOSED)
  • Center      Street OPEN
  • TUESDAY -   Seal      Joint Sand with Stabilizer
  • WEDNESDAY      AFTERNOON – Pavement Markings and Remove Detour – Open Roadway
  • THURSDAY      – Remove Temporary Signal at Eaton St / Erie St



 

 

            

2017 WEEKLY UPDATES:

Week of April 3, 2017

-  Traffic Signal Work to begin at Eaton Street and Erie Street – Traffic to be maintained –
    All work off the travel lanes

-   Asphalt Patching on Detour Routes and Repairs – Flag Control As Needed

 

Week of April 10, 2017

-  Temporary Signal at Eaton Street and Erie Street will be in Flash Mode

-  Traffic Control Devices will be delivered to project site and stage off the roadway.

Week of April 17, 2017

-          Place Signs, Sign Covers, Barricades and Detour Route and Close M-99 (Superior St) from
           Ash Street to Michigan Ave

-          Maintain Access to Business’ with Pedestrian Barricades

-          Saw cut Concrete Sidewalk and Begin Roadway Brick and Concrete Removals

-          Remove Trees

Week of April 24, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Maintain Access to Business’ with Pedestrian Barricades

-          Brick Road Removal

-          Concrete Curb and Gutter Removals

-          Concrete Sidewalk Removals

Week of May 1, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street and Erie Street to Remain Open

-          Maintain Access to Business’ with Pedestrian Barricades

-          Watermain Installation – Anticipated Service Shut Downs Identified Next Week

-          Storm Sewer Installation

Week of May 8, 2017

-         M-99 (Superior St) Closed from Ash Street to Michigan Ave

-         Cass Street to Close Mid-Week – for 2 – 3 Days

-         Erie Street to Remain Open

-         Maintain Access to Business’ with Pedestrian Barricades

-         Storm Sewer Installation

Week of May 15, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Close End of the Week – for 2 -3 Days

-          Erie Street to Remain Open

-          Pedestrians to Cross at Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Water main Installation – Erie St to Ash St – No Anticipated Service Shut Downs

-          Storm Sewer Installation to Begin End of Week

Week of May 22, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Remain Open

-          Erie Street to Remain Open

-          Pedestrians to Cross at Cass and Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Water main Pressure Testing

-          Water main Service Installation – Starting at Cass and Moving to South – Scheduled Service Shut Downs

-          Storm Sewer Installation – Starting at Cass and Moving to South

-          No Work During Memorial Day Weekend

Week of May 29, 2017 (No Work on Monday, May 29th)

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Remain Open

-          Erie Street to Close for Storm Sewer Crossing – for 2 -3 Days

-          Pedestrians to Cross at Cass and Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Water main Service Installation – Moving to the South – Scheduled Service Shut Downs

-          Storm Sewer Installation to Continue

Week of June 5, 2017 

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Remain Open

-          Erie Street to Remain Open

-          Pedestrians to Cross at Cass and Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Water main Service Lead Connections – Scheduled Service Shut Downs

-          Storm Sewer Installation to Continue

-          AT&T Installing New Ducts on West Side of S. Superior St

 

  Attached is the Progress Schedule for comparison.

-  The Water main original schedule controlling operation was to be completed on May 26th. This is not completed and is behind original schedule.

- Strom Sewer installation was scheduled as controlling operation starting on May 30th. This has already started and is ahead of schedule.

-  Brick Pavers are scheduled to begin on July 5th.

Week of June 12, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Remain Open

-          Erie Street to Remain Open

-          Pedestrians to Cross at Cass and Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Water main Service Installation – Scheduled Water Service Shut Downs for Building Cut Ins

-          Building Owners to be Notified by the City of Albion

-          Storm Sewer Installation at South End

-          AT&T Installing New Ducts on West Side of S. Superior St

 

Week of June 19, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Remain Open

-          Erie Street to Remain Open

-          Pedestrians to Cross at Cass and Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Water main Service Installation – Scheduled Water Service Shut Downs for Building Cut Ins

-          Building Owners to be Notified by the City of Albion

-          Abandon Existing Water main

-          AT&T Installing New Ducts on West Side of S. Superior St 

Week of June 26, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Remain Open

-          Erie Street to Remain Open

-          Pedestrians to Cross at Cass and Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Water main Service Installation – Scheduled Water Service Shut Downs for Building Cut Ins

-          Building Owners to be Notified by the City of Albion

-          Abandon Existing Water main

-          AT&T Installing New Ducts on West Side of S. Superior St

-          Earth Excavation and  Grading Subgrade

-          Underdrain Installation

 Week of July 2, 2017

-         NO WORK JULY 1st – JULY 4th

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Remain Open

-          Erie Street to Remain Open

-          Pedestrians to Cross at Cass and Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Earth Excavation and  Grading Subgrade

-          Underdrain Installation

-          Curb and Gutter Installation

The Cass Street and M-99 intersection is going to be closing to traffic on Wednesday, July 5th

Cass Street will be closed for approximately 2-3 weeks for water main connections, storm sewer installation,
earth excavation, sand and gravel base course and concrete base course. 

Erie Street will remain open during this time frame. 

The Closure of Cass Street has been delayed until Thursday, July 6th.

 

Week of July 17, 2017

-         M-99 (Superior St) Closed from Ash Street to Michigan Ave

-         Cass Street to Remain CLOSED

-         Erie Street to Remain Open

-         Pedestrians to Cross at Erie Street

-         Maintain Access to Business’ with Pedestrian Barricades

-         Complete Storm Sewer Cass Street to River

-         Grade and Install Curb and Gutter Ash Street to Erie Street

-         Install Concrete Valley Gutter and Bridge Deck Approach

-         Gravel Base Course Installation and Grading

-         Grade for Sidewalk

 

Week of July 24, 2017

-         M-99 (Superior St) Closed from Ash Street to Michigan Ave

-         Cass Street to Remain CLOSED

-         Erie Street to Remain Open

-         Pedestrians to Cross at Erie Street

-         Maintain Access to Business’ with Pedestrian Barricades

-         Gravel Base Course Installation

-         Grade for Sidewalk

-         Concrete Base Course Installation

 

Week of August 7, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street to Remain CLOSED

-          Erie Street to Remain Open

-          Pedestrians to Cross at Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Concrete Base Course Installation

-          Brick Installation

 

Week of August 14, 2017

-         M-99 (Superior St) Closed from Ash Street to Michigan Ave

-         Cass Street to Remain CLOSED

-         Erie Street to Remain Open

-         Pedestrians to Cross at Erie Street

-         Maintain Access to Business’ with Pedestrian Barricades

-         Brick Installation 

Week of August 21, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street Closed – Open End of the Week

-          Erie Street Open – Close End of the Week

-          Pedestrians to Cross at Erie Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Brick Installation – Center Street to Porter Street

-          Complete Asphalt Paving – Cass Street, Center Street and Porter Street

 

Week of August 28, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street Closed – Open Mid of the Week

-          Erie Street Open – Close Mid of the Week

-          Pedestrians to Cross at Erie Street Beginning of the Week and Cass Street End of the Week

-          Maintain Access to Business’ with Pedestrian Barricades

-          Brick Installation – Cass Street to Erie Street

-          Close Erie Street and Begin Water Main and Storm Sewer Work at the Intersection

-           

Week of September 4, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street Open

-          Erie Street Closed

-          Pedestrians to Cross at Cass Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Brick Installation – Center Street to Erie Street

-          Water Main and Storm Sewer Work at Erie Street

 Bricks are available for City Residence at the South West Corner of Mulberry Street and Monroe Street   

Week of September 11, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street Open

-          Erie Street Close

-          Pedestrians to Cross at Cass Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Brick Installation – Porter Street to Ash Street

-          Concrete Work at Erie Street

-          Traffic Signal Work at Erie Street

-          FESTIVAL OF FORKS

  • No Work On Project – 9:00 pm on September 14th until 7:00 am September 18th
  • Added Pedestrian Crossings at Center Street, Porter Street and Erie Street

 

Week of September 18, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street Open

-          Erie Street Closed

-          Pedestrians to Cross at Cass, Center and Porter Streets

-          Maintain Access to Business’ with Pedestrian Barricades

-          Aggregate Base Construction and Concrete Work at Erie Street

-          Water Main Bacteria Testing and Results

-          Water Services –  Cass Street and Michigan Ave

 

Week of September 25, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street Open

-          Erie Street Close

-          Pedestrians to Cross at Cass, Center and Porter Streets

-          Maintain Access to Business’ with Pedestrian Barricades

-          Complete Concrete Work at Erie Street

-          Brick Installation – Porter Street to Ash Street

-          Water Services –  Cass Street and Michigan Ave

-          Aggregate Base Work –  Cass Street and Michigan Ave

Week of October 2, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street Open

-          Erie Street Close

-          Pedestrians to Cross at Cass, Center and Porter Streets

-          Maintain Access to Business’ with Pedestrian Barricades

-          Brick Installation – Porter Street to Ash Street

-          Aggregate Base Work –  Between Cass Street and Michigan Ave

-          Concrete  –  Between Cass Street and Michigan Ave

-          Asphalt Milling at Cass St, Center St, Porter St and Ash St

-          Asphalt Paving at Cass St, Center St, Porter St and Ash St

-          Pavement Markings 

Week of October 9, 2017

-          M-99 (Superior St) Closed from Ash Street to Michigan Ave

-          Cass Street Open

-          Erie Street Closed

-          Pedestrians to Cross at Cass, Center and Porter Streets

-          Maintain Access to Business’ with Pedestrian Barricades

-          Brick Installation – Between Porter Street to Ash Street

-          Traffic Signal Work – at Michigan Ave Railroad Tracks, Cass St and Erie St

-          Concrete Sidewalk – Between Cass St and Michigan Ave

-          Pavement Markings – Erie St and Cass St

-          End of the Week – Erie Street to Open

-          End of Week – Close Michigan Ave from Post Office to Ionia St

-          End of Week – Close M-99 (Superior St) from Cass St to Mulberry St

-          End of Week – Open M-99 (Superior St) to Local Traffic Ash St to Cass St

 Week of October 16, 2017

-          M-99 (Superior St) Closed from Cass St to Mulberry St

-          Michigan Ave Closed from Post Office to Ionia St

-          Cass Street Open

-          Erie Street Open

-          Pedestrians to Cross at Michigan Ave

-          Maintain Access to Business’ with Pedestrian Barricades

-          Brick Installation – Kalamazoo River to Railroad Tracks

-          Pavement Removals – Michigan Ave to Vine St

-          Water Main Work Michigan Ave to Vine St

 

TRAFFIC PATTERN SHIFT FRIDAY OR SATURDAY

 

Friday evening or Saturday morning (Oct 13th or 14th) M-99 (Superior Street) is going to have a traffic pattern change.

M-99 is going to be closed from Mulberry Street to Cass Street including all intersections (Michigan Avenue).  This closure will remain in effect until the completion of the work in December.

M-99 is going to open to local traffic from Cass Street to Ash Street including all intersections.

Pedestrian barricades will be removed from the sidewalk from Cass Street to Ash Street and relocated to Vine Street to Cass Street.

 

Week of October 23, 2017

-          M-99 (Superior St) Closed from Cass St to Mulberry St

-          Michigan Ave Closed from Post Office to Ionia St

-          Cass Street Open

-          Erie Street Open

-          Pedestrians to Cross at Cass Street and Mulberry Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Brick Installation – Kalamazoo River to Railroad Tracks

-          Water Main Work Michigan Ave to Vine St

-          Storm Sewer Work Michigan Avenue Intersection

Week of October 30, 2017

-          M-99 (Superior St) Closed from Cass St to Mulberry St

-          Michigan Ave Closed from Post Office to Ionia St

-          Cass Street Open

-          Erie Street Open

-          Pedestrians to Cross at Cass Street and Mulberry Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Water Services Hook ups Michigan Ave to Vine St

-          Storm Sewer Work Michigan Avenue Intersection

-          Earth Excavation and Sand Subbase Installation

 

Week of November 6th, 2017

-         M-99 (Superior St) Closed from Cass St to Mulberry St

-         Michigan Ave Closed from Post Office to Ionia St

-         Cass Street Open

-         Erie Street Open

-         Pedestrians to Cross at Cass Street and Mulberry Street

-         Maintain Access to Business’ with Pedestrian Barricades

-         Traffic Signal Work Michigan Avenue

-         Earth Excavation and Sand Subbase Installation

-         Concrete Curb and Gutter, Sidewall and Concrete Base Course

-         Traffic Signal Work Michigan Avenue

 

Week of November 13th, 2017

-          M-99 (Superior St) Closed from Cass St to Mulberry St

-          Michigan Ave Closed from Post Office to Ionia St

-          Cass Street Open

-          Erie Street Open

-          Pedestrians to Cross at Cass Street and Mulberry Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Concrete Curb and Gutter, Sidewall and Concrete Base Course

-          Asphalt Paving

Week of November 20th, 2017 – NO WORK NOVEMBER 23rd – THANKSGIVING DAY

 

-          M-99 (Superior St) Closed from Cass St to Mulberry St

-          Michigan Ave Closed from Post Office to Ionia St

-          Cass Street Open

-          Erie Street Open

-          Pedestrians to Cross at Cass Street and Mulberry Street

-          Maintain Access to Business’ with Pedestrian Barricades

-          Traffic Signal Work Michigan Avenue

-          Asphalt Paving

-          Installing New Bricks

Week of November 27th, 2017

-          M-99 (Superior St) Closed from Cass St to Mulberry St

-          Michigan Ave Closed from Post Office to Ionia St

-          Cass Street Open

-          Erie Street Open

-          Maintain Access to Business’ with Pedestrian Barricades

-          Temporary Asphalt Paving on M-99 (Superior Street)

-          Pavement Markings and Permanent Signs

-          Demobilize and remove M-99 Detour from Site for Winter

-          Open M-99 and Michigan Avenue to Traffic

 

 

2018 Construction – 6 weeks to remove temporary asphalt and complete brick installation.

 



 



 

 

 





MDOTAA